A group of painters is painting the classrooms. If they paint 6 classrooms per day, they will be able to complete 1 day ahead of schedule. If they paint 4 classrooms per day, they will be 2 days behind schedule. How many classrooms are there?
6 x 1 (1 day earlier)
| |
[ ][ ][ ][ ][ ][ ]
[ ][ ][ ][ ] |
| |Number of classrooms
4 x 2 (need 2 more days)
2 u --> 4 x 2 + 6 x 1 = 14
1 u --> 14 / 2 = 7 days
7 - 1 = 6
6 x 6 = 36 classrooms
[or 7 + 2 = 9
9 x 4 = 36 classrooms]
There were 36 classrooms.